Bwcbuild.com.au

Isaac
2 years ago

Contracted to do a 5 week job. Extended to 16 weeks two weeks after starting without any justification. Finally left site at 47 weeks with work incompleted and damages to my property. Have had the Department of Fair Trading and lawyers involved. Have had to go to the Tribunal. Still not over. A complete nightmare. Do not use.
Warning they use various business names eg BWC Build, BWC waterproofing, BWC & Associates Building Professionals.
They will contract work in Sydney without revealing that the workers will be coming from the Central Coast, arriving and leaving at whatever times suit them based on avoiding traffic and consequently not fulfilling a normal tradesman days work of 7am to 3pm with lunch break. This significantly extends the time to completion.